• P-ISSN 0974-6846 E-ISSN 0974-5645

Indian Journal of Science and Technology

Article

Indian Journal of Science and Technology

Year: 2021, Volume: 14, Issue: 19, Pages: 1534-1544

Original Article

Challenges on Successful Completion and Delivery of Public Building Construction Projects: The Case of West Shoa Zone, Oromia, Ethiopia

Received Date:28 February 2021, Accepted Date:09 May 2021, Published Date:28 May 2021

Abstract

Objectives: To identify the most common challenges or constraints on successful completion and delivery of construction projects in West Shoa Zone, Oromia, Ethiopia. Besides, this study focuses on stakeholder assessment on the identified constraints and rank challenges according to their impact on time, cost, and quality of the projects. Methods: A pilot study, questionnaire, and literature review were employed to collect primary and secondary data. For this purpose, 53 different challenges were identified, categorized into six major group factors, and analyzed by relative importance index and correlation analysis using the SPSS software. Findings: The identified challenges/constraints were examined by construction stakeholders and ranked according to their impact on building construction projects. Accordingly,Inflation (RII=0.811), Inadequate design, and specification (RII=0.794), Poor planning, monitoring, and feedback mechanism (RII=0.766), Delay in solving design problems (RII=0.766), and less financing capability of the owner (RII=0.760) are the top 5 challenging factors influencing construction project delivery. Finally, the case study was conducted on selected projects to assess how many of the projects were affected by the identified challenges using performance indicators such as scheduled performance index (SPI) and cost performance index (CPI). The average value of (CPI+SPI)/2 of the five selected projects was 0.785which reveals that the projects were under performance. Novelty: The impact ranking of most challenging factors affecting successful completion and delivery of construction projects in West Shoa Zone, Oromia, Ethiopia were identified. Economic related factors such as inflation, less financing capability of the owner, and economic instability in the country were the most challenging factors. The CPI and SPI values of selected projects were used as a control to clearly understand the project’s under performance. It is recommended that the concerned body should have a common understanding of those identified constraints and solve them according to their impact ranking.

Keywords: Challenges; Successful Completion; Project Delivery; Impact Ranking; Performance Indicator

References

  1. Paul MR, Adavi PR. Effect of Labour Productivity on Project Performance. International Journal of Engineering Research & Technology. 2013;2(8):859–864. Available from: https://www.ijert.org/effect-of-labour-productivity-on-project-performance
  2. Hollermann S. Institute for Construction Engineering and Management, Bauhaus-University Weimar Marienstraße 7 Important Construction Constraints in Constraint Simulation. In: Proceedings of the 2015 Winter Simulation Conference. (pp. 3269-3280) 2015. 10.1109/WSC.2015.7408489
  3. Tanko BL, Abdullah F, Ramly ZM. Stakeholders Assessment of Constraints to Project Delivery in the Nigerian Construction Industry. International Journal of Built Environment and Sustainability. 2017;4(1):56–62. Available from: https://dx.doi.org/10.11113/ijbes.v4.n1.160
  4. Ballard. The Last Planner System of Production Control. University of Birmingham thesis
  5. Mengistu DG, Mahesh G. Challenges in developing the Ethiopian construction industry. African Journal of Science, Technology, Innovation and Development. 2020;12(4):373–384. Available from: https://dx.doi.org/10.1080/20421338.2019.1654252
  6. Ofori G. Construction in Developing Countries. Construction management and Economics. 2007;25(1):1–6. Available from: https://doi.org/10.1080/01446190601114134
  7. Gündüz M, Nielsen Y, Özdemir M. Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey. Journal of Management in Engineering. 2013;29(2):133–139. Available from: https://dx.doi.org/10.1061/(asce)me.1943-5479.0000129
  8. Arya A, Kansal R. Analyzing Delays of Construction Projects in India: Causes and Effects. International Journal of Science Technology & Engineering. 2016;3(6):66–74. Available from: https://ijste.org/Article.php?manuscript=IJSTEV3I6062
  9. Enshassi A, Mohamed S, Abushaban S. Factors affecting the performance of construction projects in the Gaza Strip. Journal of Civil Engineering and Management. 2009;15(3):269–280. Available from: https://doi.org/10.3846/1392-3730.2009.15.269-280
  10. Alyew A, MB, Reta A, Tora M. A Study on Factors Affecting Labour Productivity on Construction Projects in Wolaita, Zone Ethiopia. International Journal of Engineering Research & Technology. 2019;8(12):817–839. Available from: http://dx.doi.org/10.17577/IJERTV8IS120385
  11. Bekr AG. Factors Affecting Performance of Construction projects In Unstable Political and Economic Situations. ARPN Journal of Engineering and Applied Sciences. 2017;12(19):5384–5395. Available from: http://www.arpnjournals.com/jeas/volume_19_2017.htm
  12. Chan DWM, Kumaraswamy MM. An evaluation of construction time performance in the building industry. Building and Environment. 1996;31(6):569–578. Available from: https://dx.doi.org/10.1016/0360-1323(96)00031-5
  13. Megha D, Rajiv B. Methodology for Ranking of Causes of Delay for Residential Construction Projects in Indian Context. International Journal of Emerging Technology and Advanced Engineering. 2013;3(3):396–404. Available from: http://citeseerx.ist.psu.edu/viewdoc/summary?doi=10.1.1.413.8032
  14. Memon AH, Roslan N, Zainun NY. Improving Time Performance in Construction Projects: Perspective of Contractor. Journal of American Science. 2014;10(8):46–50. Available from: http://www.jofamericanscience.org10.7537/marsjas100814.06
  15. Mishra AK, Moktan KK. Identification of constraints in project schedule management. International Journal of Research -GRANTHAALAYAH. 2019;7(2):18–35. Available from: https://dx.doi.org/10.29121/granthaalayah.v7.i2.2019.990
  16. Chougule AA, Mudgal DN, Patil SB. A Review Paper on Quantify the Different Constraints for Delays in Infrastructure Construction Project Work and Recommending Corrective Measures for Same. International Research Journal of Engineering and Technology. 2019;6(7):3523–3525. Available from: https://www.irjet.net/volume6-issue7
  17. Le-Hoai L, Lee YD, Nguyen AT. Estimating time performance for building construction projects in Vietnam. KSCE Journal of Civil Engineering. 2013;17(1):1–8. Available from: https://dx.doi.org/10.1007/s12205-013-0862-3
  18. Kumar Mishra1 A, Bhandari S. Performance Assessment of ongoing Construction projects under Town Development Fund. Nepal. International Journal of Advanced Research in Civil & Structural Engineering. 2018;1(2):1–13.

Copyright

© 2021 Abera.This is an open-access article distributed under the terms of the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original author and source are credited. Published By Indian Society for Education and Environment (iSee)

DON'T MISS OUT!

Subscribe now for latest articles and news.